Transmission Cable Upgrade Starts Rolling Across Pasadena Streets |
What Pasadena Water and Power's five-mile project and new battery energy storage plant mean for drivers and residents |

If your commute runs along Fair Oaks Avenue or Del Mar Boulevard, expect to see orange cones for a while.
Pasadena Water and Power is scheduled to begin its Path 2 transmission cable upgrade on Monday, October 19.
The project replaces aging underground cable along a roughly five-mile route with new, maximally sized cable.
The utility says the work will significantly increase the capacity and reliability of the city's electric system.
It also supports bringing more renewable energy onto the local grid, part of Pasadena's goal of 100 percent carbon-free power by 2030.
Where crews will be working
The route starts near Fair Oaks Avenue and Glenarm Street and heads north on Fair Oaks.
It then turns east on Del Mar Boulevard, passing Caltech and Pasadena City College, before heading north on Roosevelt Avenue.
The final leg runs east on Walnut Street to just past Altadena Drive.
What drivers and neighbors should expect
Crews will work weekdays from 7 a.m. to 5 p.m., with some Saturday work from 8 a.m. to 5 p.m.
Expect light to moderate traffic control around equipment, and watch for temporary no-parking signs that move with the crew and are usually enforced for one to two days at a time.
Driveway access will be kept open in most cases, and the utility says it will coordinate directly with customers who face special access issues.
No customer power outages are expected from the work.
The project will pause during the city's December and January construction moratorium, which protects holiday shopping and Rose Parade season.
Completion is expected by late spring 2027.
A battery comes to Glenarm
The cable work is one piece of a broader grid push.
Construction is also under way on the Glenarm Battery Energy Storage System, a 25-megawatt, four-hour lithium iron phosphate battery next to the historic Glenarm Power Plant, which the city has run since 1906.
It will be Pasadena's first city-owned, utility-scale battery, storing surplus daytime solar power for the evening peak and helping the system recover faster after a major outage.
The state Energy Commission selected the project for up to $9.66 million in backup-power funding, and the utility expects it to be finished in mid-2027.
Together, the two projects signal a utility preparing for heavier demand and more renewable power.
They arrive as customers absorb the second phase of an electric rate increase that took effect October 1, adding about $1.70 to a 500-kilowatt-hour monthly bill and about $13 to a 1,000-kilowatt-hour bill.
Customers who need help with bills can call the utility's assistance line at (626) 744-4005.
Questions about the cable project can go to the Path 2 project line at (626) 744-4267. |